PofoliaPofolia ile paylaşıldı

Procedia Engineering· 2016

Şanghay Yumuşak Zeminlerinde Derin Kazı Yapımında Üstten Başlama Yöntemiyle İnşa Edilen Trafo İstasyonunun Tasarımı ve Performansı

Design and Performance of the Deep Excavation of a Substation Constructed by top-down Method in Shanghai Soft Soils

Qiping Weng, Zhonghua Xu, Zhonghu WU, Ruobiao Liu

Kısa özet

Şanghay'ın yumuşak zeminlerinde 10.800 m2'lik bir trafo istasyonu için yapılan 24 metre derinliğindeki kazı, diyafram duvarlar ve iç desteklerle deformasyon kontrolü sağlayan üstten başlama yöntemiyle başarıyla tamamlandı.

Yapay zekâ ile başlık ve abstract'tan üretildi; tam metin okunmaz.

Ana noktalar

  • Şanghay'ın yumuşak zeminlerinde 10.800 m2'lik bir trafo istasyonu için 24 metre derinliğinde bir temel çukuru kazılmıştır.
  • Karmaşık çevre koşulları ve yumuşak zemin nedeniyle üstten başlama (top-down) inşaat yöntemi tercih edilmiştir.
  • 1.2m kalınlığında diyafram duvarlar ve çok katmanlı iç destekler (çelik borulu) kullanılmıştır.
  • Enstrümantasyon verileri, üstten başlama yönteminin kazı deformasyonunu etkili bir şekilde kontrol ettiğini göstermiştir.

Yapay zekâ ile başlık ve abstract'tan üretildi; tam metin okunmaz.

Özet (abstract)

The 500kV Hongyang Underground Transmission and Substation was situated in the downtown of Shanghai city in China. The project comprised a 5-storey building above ground and three levels basements. The excavation area and depth of this project were about 10800 m2 and 24.0 m, respectively. The ground soils were mainly thick soft soils comprising Quaternary alluvial and marine deposits. Surrounding environment of this project was quite complex. Considering the excavation area and depth, the soil condition, and the protection requirements of the adjacent facilities, top-down method was adopted to construct the foundation pit of this project. The excavation was supported by 1.2 m thick diaphragm walls. Three levels of underground structures and two additional temporary struts were used to support the diaphragm wall. Steel tubes erected in bored piles were used as vertical support system. An extensive instrumentation program was carried out to monitor the performance of the deep excavation and the adjacent facilities. Monitored data of the retaining structure and the surrounding facilities were analyzed in this paper. Observation results showed that top-down method was effective to control the deformation of the excavation. Design and construction of this project can be used as a reference for similar deep excavations.

Yazarların özeti; kaynağından alınmıştır. Procedia Engineering, 2016 · DOI ↗

ÇıkarımlarPremium
Makaleye SorÜcretsiz hesapla

Ücretsiz hesapla devam et

Makaleye Sor ile bu makaleye günde 3 soru ücretsiz; makaleyi kaydet, kaynakçasını al, ilgi alanına göre her gün yeni özetler. Çıkarımlar Premium.

Web'de ücretsiz devam et

Google ya da Apple hesabınla giriş; kart istemez. Bu makaleye geri dönersin.

Telefonda:

Alan: Genel Mühendislik

General EngineeringEngineering