Where Projects Fail: Geospatial Evidence of Delays and Cancellations in Chinese Development Finance

Leoni Mendler-Krakau

Short summary

Chinese-financed projects in Africa experience delays and cancellations linked to subnational governance, with corruption increasing delays and multilateral donor presence reducing cancellations.

AI-generated from the title and abstract; the full text is not read.

Key points

  • Corruption is associated with longer project start and completion delays when analyzing within-country variation over time.
  • Co-financing and Chinese involvement in project implementation are linked to longer start delays.
  • Cancellations are less probable in regions with higher human development and multilateral donor presence.
  • Project design and subnational institutional conditions impact implementation outcomes differently for start vs. completion delays.

AI-generated from the title and abstract; the full text is not read.

Abstract

ABSTRACT Delays and cancellations can severely undermine the effectiveness of development finance. Yet, little systematic evidence exists on where and why these disruptions occur within the rapidly expanding portfolio of Chinese‐financed development projects in Africa. This paper analyses more than 3900 Chinese‐financed projects from 2000 to 2021 by combining project‐level information with regional measures of governance, conflict, development, donor presence and special economic zones. Separating delays at project start from delays at completion, we show that project design features and subnational institutional conditions are associated with implementation outcomes in phase‐specific ways. Corruption is associated with shorter start delays in cross‐sectional estimates but with longer delays at both the start and completion stages when exploiting within‐country variation over time. Co‐financing and Chinese involvement in project implementation are associated with longer start delays without a clear association with completion. Cancellations are more likely in regions with higher post‐commitment corruption levels and less common where multilateral donor activity and human development levels are higher, underscoring the importance of subnational governance and complementary donor engagement for project continuity.

The authors' abstract, as published at the source. Journal of International Development, 2026 · DOI ↗

TakeawaysPremium
Ask the paperFree account

Continue with a free account

Ask the paper: 3 free questions a day about this paper; save it, get its citation, new summaries every day for your field. Takeaways are Premium.

Continue free on the web

Sign in with Google or Apple; no card needed. You come back to this paper.

On your phone:

Field: Development

DevelopmentSocial Sciences