Using Grouting of Shield Tunneling to Reduce Settlements of Overlying Tunnels: Case Study in Shenzhen Metro Construction
- 68citations
- Q1SCImago
- 2012year
Short summary
A novel grouting control method for shield tunneling effectively reduced settlements in an existing tunnel by 70% below the allowable limit during Shenzhen Metro construction.
AI-generated from the title and abstract; the full text is not read.
Key points
- A combined observational and predefined design method was used for grouting control.
- Simultaneous backfilling grouting and direct segment hole grouting were employed.
- Real-time monitoring allowed for adjustment of grouting parameters.
- Maximum settlement of the existing tunnel was 70% of the 20 mm allowable limit.
AI-generated from the title and abstract; the full text is not read.
Abstract
Grouting control of shield tunneling is of paramount importance to reduce settlements of existing tunnels below-passed by shield tunneling along a curved alignment and in crowded urban areas. The methodology and scheme of the grouting control of shield tunneling is illustrated taking the first Earth Pressure Balanced (EPB) shield below-crossing existing interval tunnels from Kexueguan station to Dajuyuan station of the Shenzhen metro line No. 1, for example. A combination methodology of the “observational method” and the “predefined design method” was set up to deal with parameters concerning the grouting control of shield tunneling. Some parameters of the grouting control were predefined or suggested before the below-crossing, and other parameters might be adjusted during construction on the basis of the “observational method.” The scheme primarily consists of preparation work before the below-crossing, automatic motoring system used in operation tunnels, simultaneous backfilling grouting and grouting directly through segment holes. For the simultaneous backfilling grouting, enough grouting was filled in the tail void with shield advance. With the help of automatic motoring system, the grouting directly through segment holes was employed in light of the measured settlements of existing tunnels. The maximum of the final measured settlements of existing tunnels is about 70% of the predefined allowable settlement of 20 mm, which shows that the grouting control of shield tunneling is effective in reducing settlements of existing tunnels. The grouting practice can be used as references in similar conditions.
The authors' abstract, as published at the source. Journal of Construction Engineering and Management, 2012 · DOI ↗
Continue with a free account
Ask the paper: 3 free questions a day about this paper; save it, get its citation, new summaries every day for your field. Takeaways are Premium.
Continue free on the webSign in with Google or Apple; no card needed. You come back to this paper.
On your phone:
Field: General Engineering
General EngineeringEngineering